Version | 3.1.0.10513 | ||||||
---|---|---|---|---|---|---|---|
Release date |
| ||||||
Build number | 10513 | ||||||
Next scheduled release |
| ||||||
Status |
| ||||||
Upgrading instructions | Upgrading the Nanitor Server | ||||||
Nanitor Collector | 3.1.0.10513 | ||||||
Nanitor Agent | 3.1.0.10513 |
...
Four new project types have been added, these types all have different completion criteria.
Asset issue resolution
User is required to add some asset label or specify specific assets.
Considered complete when all issues for those devices have been resolved.
Asset onboarding
User is required to specify how many devices have to be added to Nanitor before the project is complete.
Optionally the user is able to specify some asset labels, which means the devices will have to have been added to those labels to be counted towards the project completion.
Asset health hardening
User is required to specify a target health score and either some asset label or specific assets to target for the hardening.
Considered complete when all assets added to the project have reached the target health score.
Upgrade/decommission assets
User is required to specify some asset labels or specific assets for the project.
Considered complete when all assets added to the project have either been upgraded to a new operating system or have been decommissioned.
...